Tool
Landed cost from Morocco: calculator
From ex-works price to delivered-to-site cost: sea freight, insurance, ECOWAS or CEMAC customs duty, levies, import VAT and port charges, for six West and Central African countries. Orders of magnitude to adjust with a real quote.
Estimated landed cost
- CIF value, arrival port: Cotonou
- 22,311 € – 23,015 €
- Net cost if VAT is recoverable
- 28,231 € – 29,093 €
- Multiplier on the ex-works price
- × 1.66 – 1.71
- Indicative sea transit from Casablanca or Tanger Med
- 12–16 days
| Item | low | high |
|---|---|---|
| Ex-works price (EXW) | 20,000 € | 20,000 € |
| Morocco side: haulage to port, export clearance, handling | 400 € | 400 € |
| Sea freight | 1,800 € | 2,500 € |
| Insurance (0.5%) | 111 € | 115 € |
| Customs duty (20 %) | 4,462 € | 4,603 € |
| Community and statistical levies (2.5 %) | 558 € | 575 € |
| Import VAT (18 %) | 4,920 € | 5,075 € |
| Arrival port: handling, customs file, forwarder, city delivery | 900 € | 900 € |
Duty applied : ECOWAS CET, pool equipment: consumer goods; pumps at 10%. Levies : statistical fee 1%, UEMOA levy 0.8–1%, ECOWAS levy 0.5%.
Guides by product
The same model applied to one product family, with the breakdown for Dakar and Abidjan.
- Landed cost of Moroccan tiles in Dakar, Abidjan and Douala
A container of tiles worth EUR 20,000 ex-works lands at 32,800 – 33,700 € in Dakar and 33,000 – 34,000 € in Abidjan. Duty, VAT, freight, transit.
- Moroccan kitchen equipment: landed cost in Dakar and Abidjan
A container of professional kitchen and laundry equipment worth EUR 50,000 ex-works: 70,400 – 71,200 € landed in Dakar, 70,400 – 71,350 € in Abidjan.
Model assumptions
Every line can be replaced by your forwarder's figure. Duty depends on the exact tariff line (HS code): ask for it before budgeting.
| Destination | Customs union | Import VAT | Levies | Freight 20' (€) | Freight 40' (€) | Transit |
|---|---|---|---|---|---|---|
| Mauritania · Nouakchott (PANPA) | CEMAC | 16 % | 1.5 % (statistical fee and national levies, order of magnitude; Mauritania belongs to neither ECOWAS nor CEMAC) | 1 100–1 600 | 1 700–2 400 | 3–5 days |
| Senegal · Dakar | ECOWAS | 18 % | 2.9 % (statistical fee 1%, UEMOA levy 1%, ECOWAS levy 0.5%, COSEC 0.4%) | 1 500–2 100 | 2 200–3 100 | 5–8 days |
| Côte d'Ivoire · Abidjan | ECOWAS | 18 % | 2.5 % (statistical fee 1%, UEMOA levy 1%, ECOWAS levy 0.5%) | 1 700–2 400 | 2 500–3 500 | 10–14 days |
| Togo · Lomé | ECOWAS | 18 % | 2.5 % (statistical fee 1%, UEMOA 0.8%, ECOWAS 0.5%, African Union 0.2%) | 1 800–2 500 | 2 600–3 600 | 12–16 days |
| Benin · Cotonou | ECOWAS | 18 % | 2.5 % (statistical fee 1%, UEMOA levy 0.8–1%, ECOWAS levy 0.5%) | 1 800–2 500 | 2 600–3 600 | 12–16 days |
| Cameroon · Douala | CEMAC | 19.25 % | 1.5 % (CEMAC integration tax 1%, OHADA 0.05%, IT fees: to confirm) | 2 100–2 900 | 3 000–4 200 | 16–22 days |
| Gabon · Libreville (Owendo) | CEMAC | 18 % | 2 % (CEMAC integration tax 1%, IT fee, reduced VAT rates on listed products) | 2 300–3 200 | 3 300–4 600 | 18–24 days |
Morocco side: EUR 400 per container (haulage, export clearance, handling; exports leave without VAT). Arrival port: EUR 900 per container (handling, customs file, forwarder, city delivery). Insurance: 0.5% of value. Exchange rate: 10.8 MAD per EUR.
Duty bands by product family
Moroccan goods enter as third-country goods, at each union's common external tariff. The calculator applies the most frequent band; the exact line may differ.
| Family | ECOWAS | CEMAC | Mauritania | Why |
|---|---|---|---|---|
| Medical gases | 5 % | 5 % | 5 % | medical equipment: reduced rate |
| Hospital beds & furniture | 5 % | 10 % | 5 % | medical furniture: 5 to 10% by tariff line |
| Sterilization | 5 % | 10 % | 5 % | sterilisers: medical capital goods |
| Laboratory equipment | 5 % | 10 % | 5 % | laboratory equipment: capital goods |
| Medical consumables & pharma | 0 % | 5 % | 0 % | medicines at 0%, consumables at 5% |
| Medical equipment & devices | 5 % | 5 % | 5 % | medical devices: reduced rate |
| Solar & energy storage | 5 % | 10 % | 5 % | panels and inverters: capital goods, frequent solar exemptions |
| Generators & power systems | 5 % | 10 % | 5 % | generators: capital goods |
| Lighting | 20 % | 30 % | 20 % | luminaires: final consumer goods |
| HVAC & cold | 10 % | 20 % | 13 % | HVAC: equipment at 10%, consumer split units often 20% |
| Lifts & escalators | 5 % | 10 % | 5 % | lifts: capital goods |
| Electrical equipment & cables | 10 % | 20 % | 13 % | cables and switchgear: 10 to 20% by tariff line |
| Sanitary ware & faucets | 20 % | 30 % | 20 % | sanitary ware and taps: final consumer goods |
| Marble & natural stone | 20 % | 30 % | 20 % | worked stone: final consumer goods |
| Ceramics & tiles | 20 % | 30 % | 20 % | ceramic tiles: final consumer goods |
| Paints, coatings & waterproofing | 20 % | 30 % | 20 % | paints and coatings: 10 to 20% by tariff line |
| Aluminium, doors, windows & glazing | 20 % | 30 % | 20 % | finished joinery: consumer goods; raw profiles at 10% |
| Plumbing, pipes & water | 10 % | 20 % | 13 % | pipes and fittings: intermediate goods |
| Professional kitchens & laundry | 10 % | 10 % | 13 % | professional kitchen and laundry equipment: capital or intermediate goods |
| Textiles, linen & workwear | 20 % | 30 % | 20 % | linen: final consumer goods |
| Furniture, FF&E & fit-out | 20 % | 30 % | 20 % | furniture: final consumer goods |
| Pools, spa & landscaping | 20 % | 30 % | 20 % | pool equipment: consumer goods; pumps at 10% |
| Safety, security & signage | 10 % | 20 % | 13 % | safety and signage: intermediate goods |
| Steel & metal structures | 10 % | 20 % | 13 % | structures and profiles: intermediate goods, some lines at 20% |
| Cement, concrete & building materials | 20 % | 20 % | 20 % | cement and structural materials: consumer-goods band, sometimes 10% by tariff line |
| Packaging | 10 % | 20 % | 13 % | packaging: intermediate goods |
| Agricultural & agro-industrial equipment | 5 % | 5 % | 5 % | agricultural machinery: capital goods, often exempt |
| Pumps, motors & compressors | 5 % | 10 % | 5 % | pumps and motors: capital goods |
| Plastics & chemicals | 10 % | 20 % | 13 % | chemicals and plastics: intermediate goods |
| Industrial machinery & equipment | 5 % | 10 % | 5 % | industrial machinery: capital goods |
| Engineering, architecture & contracting | 0 % | 0 % | 0 % | services: no customs duty, local service taxation |
Markets covered: Côte d'Ivoire, Senegal, Cameroon, Gabon, Benin, Togo, Mauritania.
Frequently asked questions
How do you calculate the landed cost of Moroccan goods in Dakar or Abidjan?+
Ex-works price, plus haulage to the Moroccan port and export clearance, plus sea freight and insurance (CIF value), plus customs duty at the common external tariff, plus community levies, plus import VAT computed on the whole, plus arrival port charges and delivery. The calculator chains these steps and shows a range.
What customs duty applies to a Moroccan product in West Africa?+
Morocco is a member of neither ECOWAS nor CEMAC: its goods are taxed at the common external tariff, 0 to 35% by category. Capital goods are generally at 5%, intermediate goods at 10%, consumer goods at 20% (ECOWAS) or 30% (CEMAC).
How much does a container from Casablanca to Dakar cost?+
Order of magnitude in 2026: EUR 1,500 to 2,100 for a 20-foot and EUR 2,200 to 3,100 for a 40-foot container, excluding port charges, for 5 to 8 days at sea. To Abidjan, count 10 to 14 days and 15 to 20% more; to Douala or Libreville, 16 to 24 days and 35 to 50% more.
Is import VAT a final cost?+
It is paid at customs clearance. A VAT-registered buyer recovers it afterwards; for an individual or a non-registered body it is a final cost. The calculator shows both readings.
Why buy in Morocco rather than Asia if the duty is the same?+
Lead time: two to three weeks at sea instead of six to eight, samples and factory visits within reach, and made-to-measure production. On a site whose opening date slips, lead time is often worth more than the price gap.